We didn't do so good at taking pictures of the plumbing. Part of that is probably because it actually went fairly quickly and only took a couple of weekends. This is a shot of the kitchen rough-in with the master bath on the other side of the walls. The strange looping construct was because I ran out of fittings but wanted to pressure test the system.
This is to be our laundry and double sink. It is not really clear in this picture, but I had to build a knee wall to get the drain pipe around that 3 inch pipe for the radon vent. We left the system under pressure every weekend we were there to have confidence in the fittings. Because of that it only took a simple twist to get a face full of water from the washing machine taps, something that Dondon discovered. You can also see in both pictures the crazy way I ran the pipes in some places. As I mention in my text, I did things backwards. Remember: do the waste pipes first, then the water pipes and finally the wires!